Campus Construction Update: June 12-19

Published:
June 12, 2017

Major activity week of June 12 through the week of June 19

  • Excavation of north pavilion
  • Excavation of foundation footings
  • Waterproofing
  • Backfill of foundation walls
  • Concrete deliveries
  • Quality control inspections prior to placing concrete
  • Under slab plumbing/electrical, south pavilion
  • Slab on grade pours, south pavilion
  • Construct elevator shafts at south pavilion
  • Layout for steel erection, south pavilion
  • Excavate bore pit on south side of Younkers (sidewalks affected)
  • Bore sleeves from south side of Younkers to HSSC
  • Site grading at well field
  • Excavate for geo well circuit piping
  • Move scaffold for elevator installation behind Carnegie
  • Revise fence route at sundial
  • Close sidewalk between Carnegie and Herrick Chapel

Installations occurring during this time period

  • Geothermal wells
  • Mud mats for footings
  • Foundation footings
  • Foundation walls
  • Underground MEP at north pavilion
  • Secondary electrical feeders off ARH transformer (diagonal sidewalk closed)

 