 |
To: The Campus Community
From: Russell Osgood
Date: June 26, 2002
Re: Campus Plan Update
It has been two years since the Board accepted the Campus Plan developed by
Shepley Bulfinch Richardson and Abbott. This plan identified our space needs and set
out a framework for contemplating which facility projects to pursue further. It helped us
to think about foreseeable needs and a realistic sequencing of any facility projects (so as
to avoid, for example, trying to build a residence hall on the old softball field without
another site at which the softball team can play). As a framework, plans are meant to
accommodate change and ours has. Set out below is an update on those facilities that
have been authorized or are being planned at this time.
I. Authorized Facilities
A. Athletic Fields
Last fall, we completed construction of new athletic fields north of
Tenth Avenue (and east of the railroad tracks). The softball team,
which needed a replacement field (to accommodate the
construction of the new residence halls), played its home games on
these fields in the spring. In the fall, both men's and women's
soccer will move to our new athletic fields and our football team
will practice there as well.
B. The Chrystal Center
The Campus Plan recommended that we move the Offices of
Admission and Financial Aid to a prominent location that would be
easy for visitors to find: the corner of Sixth Avenue and Park
Street. This fall, we will open the Chrystal Center, designed by
Herbert Lewis Kruse and Blunck, which will house the Office of
the Registrar, our Cashier, and the Office of Institutional Research
in addition to the Offices of Admission and Financial Aid.
C. Energy Centers and Related Infrastructure
Our planners and engineers recognized at the beginning of the
planning process, that any new facility would require additional
heating and cooling capacity and an improved distribution system.
This meant that a new heating/cooling facility would need to be
completed before any other new building. As a result, we
contracted with Ericksen Ellison to design a facility that would
accommodate these needs. The architects ultimately recommended
that we build a separate heating plant, north of Cowles, and
renovate the current heating/cooling plant to serve as a chilling
plant. The heating plant is near completion and the current
combined plant will be converted to a chilling plant over the next
year. In addition, we are in the process of laying improved
distribution lines underground throughout campus to ensure that
large facilities are connected to our heating/cooling system.
D. Residence Halls
The Campus Plan recommended that we add five residence halls to
be built on a new "East Campus," north of Eighth Avenue and east
of the railroad tracks. Consistent with the plan, we contracted with
William Rawn and Associates to design residence halls for that site
and we are currently building four of them. We project that three
of the four halls will be completed by August of 2003 and the
fourth one will be completed during the fall of 2003.
E. Facilities Management
The Office of Facilities Management moved into a new building
on the east side of town this spring (Sixth Avenue and Penrose).
As a result, the current Facilities Management building will be
demolished this summer to open up access to the new athletic
fields to the north and provide space for outdoor tennis courts
(should we need to move the current tennis courts to make way for
a new fieldhouse/recreation center).
F. Campus Center
The need for a new campus center was one of the motivating
factors behind originally undertaking the campus planning process.
Recognizing this need, the College has engaged Cesar Pelli and
Associates to design a new campus center, to be named for Joe
Rosenfield and sited at the center of campus. We are currently in
the design phase and Cesar Pelli projects that construction will
begin in the late winter, 2004 and completed by the spring of 2006.
The Board is also prepared to authorize the demolition of Darby
Gymnasium, which the current Campus Center design
contemplates.
G. Phase II of the Noyce Science Center
We have one of the most successful science facilities in the nation.
When renovated in the mid-nineties, we contemplated a second
phase to further improve the spaces for the sciences. In May, the
Board authorized the College to engage Holabird & Root and
Research Facilities Design (the planners and designers of Phase I)
to plan and design Phase II of the Noyce Science Center. The
program for the second phase is completed; we project that the
design will be finished by March of 2004 and that construction
could be completed by March of 2006.
II. Additional Planning- Facilities
A. Athletic Facilities
Last year, we engaged the firm of Cannon Design to develop a
program and conceptual design for an overall athletic complex,
including a new fieldhouse/recreation center. This planning
reflected the belief of many that our athletic/recreation spaces
should be improved. In addition, from a sequencing perspective,
we will need another space for those athletic functions currently
housed in Darby Gymnasium, should it be demolished.
B. Sequencing
Over the last 4 months, we have engaged in a complicated process
of determining where we could relocate offices and functions that
will need to move as a result of the construction of the Chrystal
Center, the new residence halls, the Campus Center, and Phase II
of the Noyce Science Center. For example, should Darby come
down, several offices and functions, such as the Office of
Information Technology Services and KDIC, will need to move
elsewhere. In addition, we have been exploring the best uses of
Mears Cottage, which will be completely vacant when the Chrystal
Center is occupied in the fall.
Sequencing planning is not a one-time effort. Rather, it is part of
an ongoing process to ensure that we have viable spaces, either
temporary or permanent, for all offices and functions affected by
the construction of new facilities.
|
 |