Construction Update for March 7, 2017

Published:
March 06, 2017

Activity at the HSSC site is picking up. Please be safe and aware of occurrences that may affect you.

What you need to know:

  • Deep Foundations are being installed, meaning that streets will be busy with a high volume of truck traffic all week.
  • Electrical service for the tower crane is being installed. NOTE: This will require a POWER OUTAGE for all of ARH on Saturday, March 11, approximately 8 a.m. to 11 a.m.

Major activity week of March 6 through week of March 13:

  • Excavation of south pavilion to prepare for footing installation
  • Removal of Existing Site Piping South of ARH

Installations to be aware of:

  • Shoring for excavation at Carnegie and ARH
  • Window coverings at north windows of ARH
  • Tower crane base and 1st section of tower crane
  • Full tower crane, March 17 and 18

 