Campus Construction Update: June 12-19
Jun 12, 2017
Major activity week of June 12 through the week of June 19
- Excavation of north pavilion
- Excavation of foundation footings
- Waterproofing
- Backfill of foundation walls
- Concrete deliveries
- Quality control inspections prior to placing concrete
- Under slab plumbing/electrical, south pavilion
- Slab on grade pours, south pavilion
- Construct elevator shafts at south pavilion
- Layout for steel erection, south pavilion
- Excavate bore pit on south side of Younkers (sidewalks affected)
- Bore sleeves from south side of Younkers to HSSC
- Site grading at well field
- Excavate for geo well circuit piping
- Move scaffold for elevator installation behind Carnegie
- Revise fence route at sundial
- Close sidewalk between Carnegie and Herrick Chapel
Installations occurring during this time period
- Geothermal wells
- Mud mats for footings
- Foundation footings
- Foundation walls
- Underground MEP at north pavilion
- Secondary electrical feeders off ARH transformer (diagonal sidewalk closed)