Campus Construction Update: June 5-12
Jun 5, 2017
Sidewalks will soon be affected around Younkers and closed between Carnegie and Herrick Chapel.
Major activity week of June 5 through the week of June 12
- Excavation of north pavilion
- Excavation of foundation footings
- Waterproofing
- Backfill of foundation walls
- Deliveries of rebar and concrete
- Quality control inspections prior to placing concrete
- Under slab plumbing/electrical, south pavilion
- Slab on grade pours, south pavilion
- Construct elevator shafts at south pavilion
- Excavate bore pit on south side of Younkers (sidewalks affected)
- Bore sleeve from south side of Younkers to HSSC
- Clean and grade geo field/excavate for circuit tie-ins
- Revise fence route at sundial
- Close sidewalk between Carnegie and Herrick Chapel
Installations occurring during this time period
- Geothermal wells
- Mud mats for footings
- Foundation footings
- Foundation walls
- 6’ tall metal fence at well field/west ARH transformer (closes diagonal sidewalk by transformer)
- Secondary feeders off ARH transformer